Hi experts,
I try to upgrade my productive system from ECC 6.0 to ECC 6.0 EHP7; but I have a problem in the phase start_shdi_first, it can not start and the disp+work process appear with SELW status.
The error that appear in dev_w0 is:
B DBI: init TBI BUFFER (data): start=7000000a0501000 length=14149888 end=7000000a127f900
B dbprotocol: table logging switched off for all clients
B db_tbi_install(): tbi_init_singletons() -> rc = false
B db_tbiinit failed
M *** ERROR => ThrtDatabaseEnvInit: db_init failed (4) [thrtDatabase 48]
M *** ERROR => ThrtDatabaseEnvInit failed (4) [thxxext.c 181]
M *** ERROR => ThCallHooks: event handler ThrtStartup for event CREATE_SHM failed (4) [thSos.c 2080]
M *** ERROR => ThIPCInit: hook failed [thxxhead.c 1290]
M ***LOG R19=> ThInit, ThIPCInit ( TSKH-IPC-000001) [thxxhead.c 1028]
M in_ThErrHandle: 1
M *** ERROR => ThInit: ThIPCInit (step TH_INIT, thRc ERROR-CORE-INIT_FAILED, action STOP_WP, level 1) [thxxhead.c 2149]
My system is AS/400 with more than 100GB RAM; so it is not problem of memory.
I tried to pacth the kernel, but I have the same problem.
What could be the reason?
Thanks in advance,
Regards,